Seabrook Gate Complex, CMAR

New Orleans, Louisiana

CLIENT

Alberici Constructors, Inc.

OWNER

USACE New Orleans District

PROJECT REVENUE

$2.3M

TIME

2010-2012

D.CaseStudies SeabrookPhoto 1
GRIFFIN DIFFERENCE

These solutions eliminated the need for the more expensive tremie slab method. These VE concepts saved USACE $16M with a 3-month schedule reduction from the critical path and provided temporary flood protection during construction, allowing USACE to achieve their congressionally-mandated intermediate milestone requirement for 100-year perimeter flood protection. Dewatering was performed with 42 deepwells with unwatering and rewatering pumps. personnel, Griffin achieved the required drawdown and treated for required VOCs and TSS and met the client’s needs.

THE CHALLENGE

Design and oversight of a dewatering system for the construction of a new levee wall system, vertical lift gates, and sector gates within the New Orleans IHNC. The biggest challenge to the project was a scour hole that extended to ±EL-87 caused by a previous bridge pier that crossed Navigation Canal.

THE SOLUTION

Installation of 42 deepwells, unwatering system, rewatering system, and operation and maintenance for project crossing Navigation Canal. Alberici conceptualized several accepted innovations during pre-construction that reduced risks and project costs during construction, including a temporary rock dike across the canal that reduced tidal flow to allow for use of a cofferdam and design/build dewatering system. The contractor backflled the scour hole with SP Sandy Soils and Griffin jetted deep wells that extended up to 75 ft. deep in the canal section of the project. This allowed for a subgrade of EL -28 to be achieved.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Mill Creek Diversion Chamber
Mill Creek Diversion Chamber
Learn How >
L-536 Levee Outlet Structures
L-536 Levee Outlet Structures
Learn How >
Buzzard Point
Buzzard Point
Learn How >
One Kings Bay Submarine Base
One Kings Bay Submarine Base
Learn How >
Rose Way Industrial Park
Rose Way Industrial Park
Learn How >
Clarke Creek Pump Station
Clarke Creek Pump Station
Learn How >
Project Bruin
Project Bruin
Learn How >
Fort Lauderdale Aquatic Complex (FLAC)
Fort Lauderdale Aquatic Complex (FLAC)
Learn How >
Lifetime Parking Garage and Facility
Lifetime Parking Garage and Facility
Learn How >
Des Moines University Slope Stabilization
Des Moines University Slope Stabilization
Learn How >